Construction Starts: Lyman Duff - CFI Ernst

External facade of Lyman Building
Published: 27 May 2025

Please be advised that ºÚÁÏÍø has mandated Concept P.V.R. to carry out the following project:Ìý21-028 - Lyman Duff - CFI Ernst

Description: Renovation of existing laboratories on the 6th and 7th floors to support Dr. Ernst’s research and CFI equipment.

Construction start date: June 5th 2025

Planned construction end date: June 30th 2026

Work schedule:ÌýMonday to Friday, 7am to 9pm. Works outside of building hours will be coordinated in advance.

Project Manager: guillaume.brassard [at] mcgill.ca (Guillaume Brassard)

Assistant Project Manager: christine.torres [at] mcgill.ca (Christine Torres)

Contact for building users: carmen.lampron [at] mcgill.ca (Carmen Lampron)Ìý²¹²Ô»åÌýshawn.casey [at] mcgill.ca (Shawn Casey)Ìý

-------------------------------------------------------------------------------------------------------

Scope of work:

Renovate existing laboratories on the 6th and 7th floor of the Lyman Duff Medical Building to support Dr. Ernst’s research and CFI equipment. Conform to the current ºÚÁÏÍø design standards for Laboratories and Canadian Biosafety Standards for CL2. The existing layout of the rooms is to be fully modified and modernized.

Impact & mitigation:

  • Work in the hallways on 5th, 6th and 7th floors is required and will be completed from 7pm to 7am and over a weekend. This work will be coordinated with the building users, including CMARC and Pain Center occupants with a month’s advance notice
  • Noisy work and vibration will also be coordinated in advance with impacted users
  • Service shutdowns (e.g., electrical, ventilation) will require authorization and will be coordinated with building users with advance notice
  • Freight elevator use by the contractor will be restricted to certain hours and material deliveries only (from 10am to 3pm and 6pm to 8am) with the priority given to CMARC and Pain center occupants

Safety considerations

Demolition work involving asbestos-containing materials

The project includes the removal of materials that contain asbestos. This work will be carried out under the appropriate asbestos safety protocols. This phase of the work is expected to be completed by July 2025. The safety protocols include a variety of protective measures, including sealing off the construction site from the rest of the building, the use of specialized vacuuming equipment, specialized cleaning, and daily inspections by our health and safety consultants.